{"id":15473,"date":"2025-10-28T14:55:01","date_gmt":"2025-10-28T13:55:01","guid":{"rendered":"https:\/\/ekton.us\/?p=15473"},"modified":"2025-10-30T15:48:51","modified_gmt":"2025-10-30T14:48:51","slug":"wbs-control-accounts-and-cbs-erp-oil-gas-part-1-the-1-wbs-mistake-and-how-to-fix-it","status":"publish","type":"post","link":"https:\/\/ekton.us\/zh\/wbs-control-accounts-and-cbs-erp-oil-gas-part-1-the-1-wbs-mistake-and-how-to-fix-it\/","title":{"rendered":"\u201cThe #1 WBS Mistake in Oil & Gas Projects \u2014 And How to Fix It with CBS, Control Accounts, and AWP\u201d"},"content":{"rendered":"
\n
\"\"<\/figure>\n
\n

\u00a0<\/h3>\n

WBS in Oil & Gas Projects: The #1 Mistake Killing EVM Systems \u2014 and How to Fix<\/strong><\/h3>\n<\/figure>\n<\/figure>\n

\u00a0<\/p>\n

\u00a0<\/p>\n

\n
By:<\/strong> Simao Pedro Bessala, PMP, PMI-RMP, PMI-SP \u2014 Sr. Project Controls & BI Consultant, CEO at Ekton Project Analytics (ekton.us)<\/figure>\n<\/figure>\n

\u00a0<\/p>\n

<\/p>\n

What the WBS is not<\/em><\/strong><\/h2>\n

<\/p>\n

    \n
  • \n
      <\/ul>\n<\/li>\n<\/ul>\n
        \n
      • \n
          \n
        • Not phases<\/strong> (ENG\/PROC\/CONST\/MC\/COM) \u2014 those are execution lenses.<\/li>\n<\/ul>\n<\/li>\n<\/ul>\n

          <\/p>\n

            \n
          • \n
              \n
            • Not disciplines<\/strong> (CIV\/MEC\/PIP\/ELE\/IST\/TLC) \u2014 those are performing lenses.<\/li>\n<\/ul>\n<\/li>\n<\/ul>\n

              <\/p>\n

                \n
              • \n
                  \n
                • Not contractors or budgets<\/strong> \u2014 those live in OBS and CBS\/ERP, and as attributes on work packages.<\/li>\n<\/ul>\n<\/li>\n<\/ul>\n

                  <\/p>\n

                    \n
                  • \n
                      \n
                    • Not Areas<\/strong> \u2014 Areas are for AWP\/workface flow, not scope.<\/li>\n<\/ul>\n<\/li>\n<\/ul>\n

                      <\/p>\n

                      <\/p>\n

                      Where Areas fit (without corrupting the WBS)<\/strong><\/h2>\n

                      <\/p>\n

                      Areas are vital for AWP<\/strong> and crew flow\u2014but Areas are not scope<\/strong>. Keep them orthogonal to the WBS:<\/p>\n

                      <\/p>\n

                      Two Foundations of Work<\/strong><\/h3>\n

                      <\/p>\n

                      1) Area-only (enabling\/physical)<\/strong><\/p>\n

                      <\/p>\n

                      Earthworks, foundations, piperack steel, building shell, scaffolds, roads. Acceptance is geometric\/physical<\/strong>, not by process system.<\/p>\n

                      <\/p>\n

                      \u00a0\u2192 Host under a formal Infrastructure\/Enabling System<\/strong> in each Unit (e.g., Unit 420 \/ System 420-900: Infrastructure & Enabling<\/em>), so the WBS leaf remains a System<\/strong>.<\/p>\n

                      <\/p>\n

                      2) Dual foundation (Area + System\/Sub-system)<\/strong><\/p>\n

                      <\/p>\n

                      Scope that will be handed over functionally<\/strong>: piping spools & tests, mechanical hook-ups, cable pulls & terminations, loops, hydro\/IR, pre-comm\/commissioning.<\/p>\n

                      <\/p>\n

                      \u2192 Lives under the real System\/Sub-system<\/strong>; Area<\/strong> stays as a WP attribute<\/strong> for AWP release and look-ahead.<\/p>\n

                      <\/p>\n

                      Result:<\/strong> Flow by Area<\/strong> without corrupting scope<\/strong>\u2014and clean handover by System<\/strong>.<\/p>\n

                      <\/p>\n

                      Accountability lives at the WBS\u00d7OBS intersection<\/strong><\/h2>\n

                      <\/p>\n

                      Control Account (CA) = System \u00d7 OBS leaf (owner\/team).<\/strong><\/p>\n

                      <\/p>\n

                        \n
                      • \n
                          <\/ul>\n<\/li>\n<\/ul>\n
                            \n
                          • \n
                              \n
                            • A CA fixes responsibility only<\/strong> (one CAM).<\/li>\n<\/ul>\n<\/li>\n<\/ul>\n

                              <\/p>\n

                                \n
                              • \n
                                  \n
                                • No phase or discipline implied<\/strong> at CA level.<\/li>\n<\/ul>\n<\/li>\n<\/ul>\n

                                  <\/p>\n

                                    \n
                                  • \n
                                      \n
                                    • Work Packages (WPs) live inside<\/strong> the CA.<\/li>\n<\/ul>\n<\/li>\n<\/ul>\n

                                      <\/p>\n

                                      <\/p>\n

                                      Planning Packages (embrace uncertainty, govern it)<\/strong><\/h2>\n

                                      <\/p>\n

                                      At end-of-FEED something is always missing (tags not fully mapped, IFC incomplete, hydro\/loop packs open). Don\u2019t pollute the WBS to cope\u2014use Planning Packages (PPs)<\/strong>:<\/p>\n

                                      <\/p>\n

                                        \n
                                      • \n
                                          <\/ul>\n<\/li>\n<\/ul>\n
                                            \n
                                          • \n
                                              \n
                                            • PPs live inside the correct CA<\/strong> (so ownership is right).<\/li>\n<\/ul>\n<\/li>\n<\/ul>\n

                                              <\/p>\n

                                                \n
                                              • \n
                                                  \n
                                                • Budgeted, time-phased, logic-tied<\/strong> to the System turnover.<\/li>\n<\/ul>\n<\/li>\n<\/ul>\n

                                                  <\/p>\n

                                                    \n
                                                  • \n
                                                      \n
                                                    • Earn zero EV<\/strong> until converted to executable WPs.<\/li>\n<\/ul>\n<\/li>\n<\/ul>\n

                                                      <\/p>\n

                                                        \n
                                                      • \n
                                                          \n
                                                        • Carry a ReasonCode<\/strong> (ENG_NOT_READY, MAT_NOT_READY, ITR_PENDING, ACCESS_NOT_READY,<\/em> etc.).<\/li>\n<\/ul>\n<\/li>\n<\/ul>\n

                                                          <\/p>\n

                                                            \n
                                                          • \n
                                                              \n
                                                            • Convert \u226490 days<\/strong> before execution or<\/strong> when maturity gates are met (\u224885% tags mapped, \u224880% IFC<\/strong>).<\/li>\n<\/ul>\n<\/li>\n<\/ul>\n

                                                              <\/p>\n

                                                              <\/p>\n

                                                              Canonical Work-Package schema (simple and scalable)<\/strong><\/h2>\n

                                                              <\/p>\n

                                                              WP = CA \u00d7 Phase \u00d7 Discipline \u00d7 EV Method \u00d7 Area \u00d7 Timebox<\/p>\n

                                                              <\/p>\n

                                                                \n
                                                              • \n
                                                                  <\/ul>\n<\/li>\n<\/ul>\n
                                                                    \n
                                                                  • \n
                                                                      \n
                                                                    • One WP \u2192 one CA<\/strong>; single Phase; single Discipline; one Area.<\/li>\n<\/ul>\n<\/li>\n<\/ul>\n

                                                                      <\/p>\n

                                                                        \n
                                                                      • \n
                                                                          \n
                                                                        • IWPs are 1\u20132 week slices released only with Full-Kit<\/strong>.<\/li>\n<\/ul>\n<\/li>\n<\/ul>\n

                                                                          <\/p>\n

                                                                          <\/p>\n

                                                                          Full-Kit gate (pass\/fail):<\/strong> Permits \u25a2 | IFC \u25a2 | Materials \u25a2 | Tools\/Equip \u25a2 | Access\/Scaffold \u25a2 | Predecessors \u25a2 | QA\/ITRs \u25a2 | Interfaces\/LOTO \u25a2<\/p>\n

                                                                          <\/p>\n

                                                                          Thresholds:<\/strong> Green \u226595% (release) | Amber 85\u201394% (exception sign-off) | Red <85% (do not release)<\/p>\n

                                                                          <\/p>\n

                                                                          Data backbone (so leaders get real answers)<\/strong><\/h2>\n

                                                                          <\/p>\n

                                                                          Use a tag-level EPFC (+ Pre-Comm\/Comm)<\/strong> register keyed to Area<\/strong> and<\/em> Unit+System\/Sub-system<\/strong>:<\/p>\n

                                                                          <\/p>\n

                                                                            \n
                                                                          • \n
                                                                              <\/ul>\n<\/li>\n<\/ul>\n
                                                                                \n
                                                                              • \n
                                                                                  \n
                                                                                • E<\/strong>ngineering: IFC status\/holds<\/li>\n<\/ul>\n<\/li>\n<\/ul>\n

                                                                                  <\/p>\n

                                                                                    \n
                                                                                  • \n
                                                                                      \n
                                                                                    • P<\/strong>rocurement: MR\/PO\/delivery<\/li>\n<\/ul>\n<\/li>\n<\/ul>\n

                                                                                      <\/p>\n

                                                                                        \n
                                                                                      • \n
                                                                                          \n
                                                                                        • F<\/strong>abrication: spools\/steel % + NDE<\/li>\n<\/ul>\n<\/li>\n<\/ul>\n

                                                                                          <\/p>\n

                                                                                            \n
                                                                                          • \n
                                                                                              \n
                                                                                            • C<\/strong>onstruction: installed\/NDE\/reinstated<\/li>\n<\/ul>\n<\/li>\n<\/ul>\n

                                                                                              <\/p>\n

                                                                                                \n
                                                                                              • \n
                                                                                                  \n
                                                                                                • Pre-Comm:<\/strong> hydro pack ID & status, IR tests, flushing<\/li>\n<\/ul>\n<\/li>\n<\/ul>\n

                                                                                                  <\/p>\n

                                                                                                    \n
                                                                                                  • \n
                                                                                                      \n
                                                                                                    • Comm:<\/strong> loops closed, energization, function tests<\/li>\n<\/ul>\n<\/li>\n<\/ul>\n

                                                                                                      <\/p>\n

                                                                                                      <\/p>\n

                                                                                                      With that single source, your control room can show per Unit+System<\/strong>:<\/p>\n

                                                                                                      <\/p>\n

                                                                                                        \n
                                                                                                      • \n
                                                                                                          <\/ul>\n<\/li>\n<\/ul>\n
                                                                                                            \n
                                                                                                          • \n
                                                                                                              \n
                                                                                                            • Lateness in working days<\/strong> (longest path to turnover, native calendars respected)<\/li>\n<\/ul>\n<\/li>\n<\/ul>\n

                                                                                                              <\/p>\n

                                                                                                                \n
                                                                                                              • \n
                                                                                                                  \n
                                                                                                                • Top-2 slip drivers<\/strong> (the two activities with the largest BL\u2192FC \u0394Finish)<\/li>\n<\/ul>\n<\/li>\n<\/ul>\n

                                                                                                                  <\/p>\n

                                                                                                                    \n
                                                                                                                  • \n
                                                                                                                      \n
                                                                                                                    • Hydro\/Loop readiness<\/strong>, punch burndown, PP exposure<\/strong><\/li>\n<\/ul>\n<\/li>\n<\/ul>\n

                                                                                                                      <\/p>\n

                                                                                                                      <\/p>\n

                                                                                                                      \u00a0\u2026and, in the same breath, list which IWPs in Area A06<\/strong> are Green<\/strong> for next week.<\/p>\n

                                                                                                                      <\/p>\n

                                                                                                                      Tiny example<\/strong><\/p>\n

                                                                                                                      <\/p>\n

                                                                                                                      Unit 420 \/ System 420-001 (Fuel Gas Conditioning)<\/em> shows +14 WD late<\/strong> driven by Spool Lot C (+7 WD)<\/strong> and Loop FG-LT-211 (+5 WD)<\/strong>. Yet A06<\/strong> has two IWPs Green<\/strong> next week because they don\u2019t depend on those items. Flow today; explainable handover tomorrow.<\/p>\n

                                                                                                                      <\/p>\n

                                                                                                                      Examples you can copy<\/strong><\/h2>\n

                                                                                                                      <\/p>\n

                                                                                                                      Area-only (hosted under Unit 420 \/ System 420-900: Infrastructure & Enabling<\/em>)<\/strong><\/h3>\n

                                                                                                                      <\/p>\n

                                                                                                                        \n
                                                                                                                      • \n
                                                                                                                          <\/ul>\n<\/li>\n<\/ul>\n
                                                                                                                            \n
                                                                                                                          • \n
                                                                                                                              \n
                                                                                                                            • Piperack steel (A06):<\/strong><\/li>\n<\/ul>\n<\/li>\n<\/ul>\n

                                                                                                                              <\/p>\n

                                                                                                                              <\/p>\n

                                                                                                                              \u00a0WP-420900\u2013EPC.TeamStrucInst\u2013CONSTR\u2013STR\u2013QTY\u2013A06\u20132025W13<\/p>\n

                                                                                                                              <\/p>\n

                                                                                                                                \n
                                                                                                                              • \n
                                                                                                                                  <\/ul>\n<\/li>\n<\/ul>\n
                                                                                                                                    \n
                                                                                                                                  • \n
                                                                                                                                      \n
                                                                                                                                    • Earthworks (A105):<\/strong><\/li>\n<\/ul>\n<\/li>\n<\/ul>\n

                                                                                                                                      <\/p>\n

                                                                                                                                      <\/p>\n

                                                                                                                                      \u00a0WP-420900\u2013EPC.TeamCivil\u2013CONSTR\u2013CIV\u2013QTY\u2013A105\u20132025W09<\/p>\n

                                                                                                                                      <\/p>\n

                                                                                                                                        \n
                                                                                                                                      • \n
                                                                                                                                          <\/ul>\n<\/li>\n<\/ul>\n
                                                                                                                                            \n
                                                                                                                                          • \n
                                                                                                                                              \n
                                                                                                                                            • Building shell for Substation 01 (A06):<\/strong><\/li>\n<\/ul>\n<\/li>\n<\/ul>\n

                                                                                                                                              <\/p>\n

                                                                                                                                              <\/p>\n

                                                                                                                                              \u00a0WP-420900\u2013EPC.TeamBuilding\u2013CONSTR\u2013ARC\u2013QTY\u2013A06\u20132025W17<\/p>\n

                                                                                                                                              <\/p>\n

                                                                                                                                                \n
                                                                                                                                              • \n
                                                                                                                                                  <\/ul>\n<\/li>\n<\/ul>\n
                                                                                                                                                    \n
                                                                                                                                                  • \n
                                                                                                                                                      \n
                                                                                                                                                    • Trenches & duct banks (A06):<\/strong><\/li>\n<\/ul>\n<\/li>\n<\/ul>\n

                                                                                                                                                      <\/p>\n

                                                                                                                                                      <\/p>\n

                                                                                                                                                      \u00a0WP-420900\u2013EPC.TeamCivilUG\u2013CONSTR\u2013CIV\u2013QTY\u2013A06\u20132025W12<\/p>\n

                                                                                                                                                      <\/p>\n

                                                                                                                                                      \u00a0(Corridor civils = Area-only; services inside become Dual later.)<\/em><\/p>\n

                                                                                                                                                      <\/p>\n

                                                                                                                                                      Dual foundation (under the real System; keep Area on the WP)<\/strong><\/h3>\n

                                                                                                                                                      <\/p>\n

                                                                                                                                                        \n
                                                                                                                                                      • \n
                                                                                                                                                          <\/ul>\n<\/li>\n<\/ul>\n
                                                                                                                                                            \n
                                                                                                                                                          • \n
                                                                                                                                                              \n
                                                                                                                                                            • Piping install (A06):<\/strong><\/li>\n<\/ul>\n<\/li>\n<\/ul>\n

                                                                                                                                                              <\/p>\n

                                                                                                                                                              <\/p>\n

                                                                                                                                                              \u00a0WP-420001\u2013EPC.TeamPipInstal\u2013CONSTR\u2013PIP\u2013QTY\u2013A06\u20132025W18<\/p>\n

                                                                                                                                                              <\/p>\n

                                                                                                                                                              \u00a0(Subsystem 420-001-210; Hydro H-420-07)<\/em><\/p>\n

                                                                                                                                                              <\/p>\n

                                                                                                                                                                \n
                                                                                                                                                              • \n
                                                                                                                                                                  <\/ul>\n<\/li>\n<\/ul>\n
                                                                                                                                                                    \n
                                                                                                                                                                  • \n
                                                                                                                                                                      \n
                                                                                                                                                                    • Electrical pulls\/terms (A06, SubcontractorB):<\/strong><\/li>\n<\/ul>\n<\/li>\n<\/ul>\n

                                                                                                                                                                      <\/p>\n

                                                                                                                                                                      <\/p>\n

                                                                                                                                                                      \u00a0WP-420001\u2013SubContrB.Electrical\u2013CONSTR\u2013ELE\u2013QTY\u2013A06\u20132025W19<\/p>\n

                                                                                                                                                                      <\/p>\n

                                                                                                                                                                      \u00a0(Loops FG-LT-211 set)<\/em><\/p>\n

                                                                                                                                                                      <\/p>\n

                                                                                                                                                                        \n
                                                                                                                                                                      • \n
                                                                                                                                                                          <\/ul>\n<\/li>\n<\/ul>\n
                                                                                                                                                                            \n
                                                                                                                                                                          • \n
                                                                                                                                                                              \n
                                                                                                                                                                            • Pre-commissioning:<\/strong><\/li>\n<\/ul>\n<\/li>\n<\/ul>\n

                                                                                                                                                                              <\/p>\n

                                                                                                                                                                              <\/p>\n

                                                                                                                                                                              \u00a0WP-420001\u2013EPC.TeamPipInstal\u2013PRECOMM\u2013PIP\u2013WM\u2013A06\u20132025W22<\/p>\n

                                                                                                                                                                              <\/p>\n

                                                                                                                                                                              \u00a0WP-420001\u2013SubContrB.Electrical\u2013PRECOMM\u2013ELE\u2013WM\u2013A06\u20132025W22<\/p>\n

                                                                                                                                                                              <\/p>\n

                                                                                                                                                                                \n
                                                                                                                                                                              • \n
                                                                                                                                                                                  <\/ul>\n<\/li>\n<\/ul>\n
                                                                                                                                                                                    \n
                                                                                                                                                                                  • \n
                                                                                                                                                                                      \n
                                                                                                                                                                                    • Commissioning:<\/strong><\/li>\n<\/ul>\n<\/li>\n<\/ul>\n

                                                                                                                                                                                      <\/p>\n

                                                                                                                                                                                      <\/p>\n

                                                                                                                                                                                      \u00a0WP-420001\u2013EPC.Commissioning\u2013COMM\u2013MULTI\u2013MS\u2013A06\u20132025W24<\/p>\n

                                                                                                                                                                                      <\/p>\n

                                                                                                                                                                                      Planning Packages (inside the right CA)<\/strong><\/h2>\n

                                                                                                                                                                                      <\/p>\n

                                                                                                                                                                                        \n
                                                                                                                                                                                      • \n
                                                                                                                                                                                          <\/ul>\n<\/li>\n<\/ul>\n
                                                                                                                                                                                            \n
                                                                                                                                                                                          • \n
                                                                                                                                                                                              \n
                                                                                                                                                                                            • Piping Eng (SubcontractorA):<\/strong><\/li>\n<\/ul>\n<\/li>\n<\/ul>\n

                                                                                                                                                                                              <\/p>\n

                                                                                                                                                                                              <\/p>\n

                                                                                                                                                                                              \u00a0PP-420001\u2013EPC.SubContrA.PipingEngTeam\u2013001 (ENG_NOT_READY) \u2192 converts when IFC isos mature (\u226490 days)<\/p>\n

                                                                                                                                                                                              <\/p>\n

                                                                                                                                                                                                \n
                                                                                                                                                                                              • \n
                                                                                                                                                                                                  <\/ul>\n<\/li>\n<\/ul>\n
                                                                                                                                                                                                    \n
                                                                                                                                                                                                  • \n
                                                                                                                                                                                                      \n
                                                                                                                                                                                                    • Piping Install:<\/strong><\/li>\n<\/ul>\n<\/li>\n<\/ul>\n

                                                                                                                                                                                                      <\/p>\n

                                                                                                                                                                                                      <\/p>\n

                                                                                                                                                                                                      \u00a0PP-420001\u2013EPC.TeamPipInstal\u2013001 (MAT_NOT_READY \/ ACCESS_NOT_READY)<\/p>\n

                                                                                                                                                                                                      <\/p>\n

                                                                                                                                                                                                        \n
                                                                                                                                                                                                      • \n
                                                                                                                                                                                                          <\/ul>\n<\/li>\n<\/ul>\n
                                                                                                                                                                                                            \n
                                                                                                                                                                                                          • \n
                                                                                                                                                                                                              \n
                                                                                                                                                                                                            • Electrical (SubcontractorB):<\/strong><\/li>\n<\/ul>\n<\/li>\n<\/ul>\n

                                                                                                                                                                                                              <\/p>\n

                                                                                                                                                                                                              <\/p>\n

                                                                                                                                                                                                              \u00a0PP-420001\u2013SubContrB.Electrical\u2013001 (VENDOR_DATA_PENDING)<\/p>\n

                                                                                                                                                                                                              <\/p>\n

                                                                                                                                                                                                                \n
                                                                                                                                                                                                              • \n
                                                                                                                                                                                                                  <\/ul>\n<\/li>\n<\/ul>\n
                                                                                                                                                                                                                    \n
                                                                                                                                                                                                                  • \n
                                                                                                                                                                                                                      \n
                                                                                                                                                                                                                    • Pre-Comm (Electrical):<\/strong><\/li>\n<\/ul>\n<\/li>\n<\/ul>\n

                                                                                                                                                                                                                      <\/p>\n

                                                                                                                                                                                                                      <\/p>\n

                                                                                                                                                                                                                      \u00a0PP-420001\u2013SubContrB.Electrical\u2013PRECOMM\u2013001 (ITR_PENDING)<\/p>\n

                                                                                                                                                                                                                      <\/p>\n

                                                                                                                                                                                                                      Good vs. Bad (at a glance)<\/strong><\/h2>\n

                                                                                                                                                                                                                      <\/p>\n

                                                                                                                                                                                                                      Bad<\/strong><\/p>\n

                                                                                                                                                                                                                      <\/p>\n

                                                                                                                                                                                                                      \u00a0361 Fuel Gas \u2192 Engineering<\/em> \u2192 Piping<\/em> \u2192 Cable trays<\/em> (methods & trades).<\/p>\n

                                                                                                                                                                                                                      <\/p>\n

                                                                                                                                                                                                                      \u00a0\u21b3 Mixing scope with execution. Every plan change forces re-wiring.<\/p>\n

                                                                                                                                                                                                                      <\/p>\n

                                                                                                                                                                                                                      Good<\/strong><\/p>\n

                                                                                                                                                                                                                      <\/p>\n

                                                                                                                                                                                                                      \u00a0361-001 Fuel Gas System \u2192 361-001-002 Distribution to Unit X (deliverables).<\/p>\n

                                                                                                                                                                                                                      <\/p>\n

                                                                                                                                                                                                                      \u00a0Execution lives on WPs with attributes (Phase, Discipline, Area<\/strong>, contractor, packs, loops).<\/p>\n

                                                                                                                                                                                                                      <\/p>\n

                                                                                                                                                                                                                      Fix it in five moves<\/strong><\/h2>\n

                                                                                                                                                                                                                      <\/p>\n

                                                                                                                                                                                                                        \n
                                                                                                                                                                                                                      1. \n
                                                                                                                                                                                                                          <\/ol>\n<\/li>\n<\/ol>\n
                                                                                                                                                                                                                            \n
                                                                                                                                                                                                                          1. \n
                                                                                                                                                                                                                              \n
                                                                                                                                                                                                                            1. Redraft leaves as handover-testable scope<\/strong>.<\/li>\n<\/ol>\n<\/li>\n<\/ol>\n

                                                                                                                                                                                                                              <\/p>\n

                                                                                                                                                                                                                                \n
                                                                                                                                                                                                                              1. \n
                                                                                                                                                                                                                                  \n
                                                                                                                                                                                                                                1. Align leaves to turnover boundaries<\/strong> (systems\/sub-systems, packs, loops).<\/li>\n<\/ol>\n<\/li>\n<\/ol>\n

                                                                                                                                                                                                                                  <\/p>\n

                                                                                                                                                                                                                                    \n
                                                                                                                                                                                                                                  1. \n
                                                                                                                                                                                                                                      \n
                                                                                                                                                                                                                                    1. Keep contractors\/phases\/disciplines\/Areas<\/strong> as WP attributes<\/strong>.<\/li>\n<\/ol>\n<\/li>\n<\/ol>\n

                                                                                                                                                                                                                                      <\/p>\n

                                                                                                                                                                                                                                        \n
                                                                                                                                                                                                                                      1. \n
                                                                                                                                                                                                                                          \n
                                                                                                                                                                                                                                        1. Use higher WBS nodes only for legitimate aggregation (packages, buildings).<\/li>\n<\/ol>\n<\/li>\n<\/ol>\n

                                                                                                                                                                                                                                          <\/p>\n

                                                                                                                                                                                                                                            \n
                                                                                                                                                                                                                                          1. \n
                                                                                                                                                                                                                                              \n
                                                                                                                                                                                                                                            1. Freeze the structure<\/strong>; manage change via baseline control\u2014not re-wiring.<\/li>\n<\/ol>\n<\/li>\n<\/ol>\n

                                                                                                                                                                                                                                              <\/p>\n

                                                                                                                                                                                                                                              <\/p>\n

                                                                                                                                                                                                                                              Bottom line<\/strong><\/h2>\n

                                                                                                                                                                                                                                              <\/p>\n

                                                                                                                                                                                                                                              A clean WBS (leaf = System\/Sub-system<\/strong>) + Infrastructure Systems<\/strong> for Area-only work + CAs at WBS\u00d7OBS<\/strong> + Planning Packages<\/strong> for immaturity gives you two truths you must manage at once:<\/p>\n

                                                                                                                                                                                                                                              <\/p>\n

                                                                                                                                                                                                                                                \n
                                                                                                                                                                                                                                              • \n
                                                                                                                                                                                                                                                  <\/ul>\n<\/li>\n<\/ul>\n
                                                                                                                                                                                                                                                    \n
                                                                                                                                                                                                                                                  • \n
                                                                                                                                                                                                                                                      \n
                                                                                                                                                                                                                                                    • Flow today<\/strong> (AWP by Area; release only with Full-Kit), and<\/li>\n<\/ul>\n<\/li>\n<\/ul>\n

                                                                                                                                                                                                                                                      <\/p>\n

                                                                                                                                                                                                                                                        \n
                                                                                                                                                                                                                                                      • \n
                                                                                                                                                                                                                                                          \n
                                                                                                                                                                                                                                                        • Explainable, auditable handover tomorrow<\/strong> (by System\/Sub-system with the two biggest delay drivers named in working days<\/strong>).<\/li>\n<\/ul>\n<\/li>\n<\/ul>\n

                                                                                                                                                                                                                                                          <\/p>\n

                                                                                                                                                                                                                                                          <\/p>\n

                                                                                                                                                                                                                                                          Part 2 (next):<\/strong> How many CAs per leaf, zero\/one\/many patterns, and why one CAM per CA<\/strong> is non-negotiable.<\/p>\n

                                                                                                                                                                                                                                                          <\/p>\n

                                                                                                                                                                                                                                                          Work with Ekton Project Analytics \u2014 WBS Foundations (Oil & Gas)<\/strong><\/p>\n

                                                                                                                                                                                                                                                          <\/p>\n

                                                                                                                                                                                                                                                          \u00a0We help teams design deliverable-oriented WBS structures aligned to turnover & commissioning.<\/p>\n

                                                                                                                                                                                                                                                          <\/p>\n

                                                                                                                                                                                                                                                            \n
                                                                                                                                                                                                                                                          • \n
                                                                                                                                                                                                                                                              <\/ul>\n<\/li>\n<\/ul>\n
                                                                                                                                                                                                                                                                \n
                                                                                                                                                                                                                                                              • \n
                                                                                                                                                                                                                                                                  \n
                                                                                                                                                                                                                                                                • 1-Day WBS & Turnover Design Workshop:<\/strong> systems\/sub-systems, boundaries, packs, decision rules<\/li>\n<\/ul>\n<\/li>\n<\/ul>\n

                                                                                                                                                                                                                                                                  <\/p>\n

                                                                                                                                                                                                                                                                    \n
                                                                                                                                                                                                                                                                  • \n
                                                                                                                                                                                                                                                                      \n
                                                                                                                                                                                                                                                                    • Executive Briefing (90 min):<\/strong> the orthogonality principle\u2014why phases\/disciplines\/Areas<\/strong> are attributes, not WBS branches<\/li>\n<\/ul>\n<\/li>\n<\/ul>\n

                                                                                                                                                                                                                                                                      <\/p>\n

                                                                                                                                                                                                                                                                        \n
                                                                                                                                                                                                                                                                      • \n
                                                                                                                                                                                                                                                                          \n
                                                                                                                                                                                                                                                                        • Deliverables:<\/strong> draft WBS leaf map, review checklist, governance playbook<\/li>\n<\/ul>\n<\/li>\n<\/ul>\n

                                                                                                                                                                                                                                                                          <\/p>\n

                                                                                                                                                                                                                                                                          <\/p>\n

                                                                                                                                                                                                                                                                          Book a discovery call: ekton.us\/consulting<\/p>\n

                                                                                                                                                                                                                                                                          <\/p>\n

                                                                                                                                                                                                                                                                          Follow for practical #WBS #EVM #AWP #EarnedSchedule #Completions #OilAndGas<\/p>\n

                                                                                                                                                                                                                                                                          <\/p>\n

                                                                                                                                                                                                                                                                          \"WBS,<\/figure>\n

                                                                                                                                                                                                                                                                          <\/p>\n

                                                                                                                                                                                                                                                                          <\/p>","protected":false},"excerpt":{"rendered":"

                                                                                                                                                                                                                                                                          \u00a0 WBS in Oil & Gas Projects: The #1 Mistake Killing EVM Systems \u2014 and How to Fix \u00a0 \u00a0 By: Simao Pedro Bessala, PMP, PMI-RMP, PMI-SP \u2014 Sr. Project Controls & BI Consultant, CEO at Ekton Project Analytics (ekton.us) \u00a0 What the WBS is not Not phases (ENG\/PROC\/CONST\/MC\/COM) \u2014 those are execution lenses. Not […]<\/p>","protected":false},"author":11,"featured_media":15478,"comment_status":"open","ping_status":"open","sticky":false,"template":"","format":"standard","meta":{"site-sidebar-layout":"no-sidebar","site-content-layout":"","ast-site-content-layout":"full-width-container","site-content-style":"default","site-sidebar-style":"default","ast-global-header-display":"","ast-banner-title-visibility":"","ast-main-header-display":"","ast-hfb-above-header-display":"","ast-hfb-below-header-display":"","ast-hfb-mobile-header-display":"","site-post-title":"","ast-breadcrumbs-content":"","ast-featured-img":"","footer-sml-layout":"","theme-transparent-header-meta":"","adv-header-id-meta":"","stick-header-meta":"","header-above-stick-meta":"","header-main-stick-meta":"","header-below-stick-meta":"","astra-migrate-meta-layouts":"set","ast-page-background-enabled":"default","ast-page-background-meta":{"desktop":{"background-color":"var(--ast-global-color-4)","background-image":"","background-repeat":"repeat","background-position":"center center","background-size":"auto","background-attachment":"scroll","background-type":"","background-media":"","overlay-type":"","overlay-color":"","overlay-opacity":"","overlay-gradient":""},"tablet":{"background-color":"","background-image":"","background-repeat":"repeat","background-position":"center center","background-size":"auto","background-attachment":"scroll","background-type":"","background-media":"","overlay-type":"","overlay-color":"","overlay-opacity":"","overlay-gradient":""},"mobile":{"background-color":"","background-image":"","background-repeat":"repeat","background-position":"center center","background-size":"auto","background-attachment":"scroll","background-type":"","background-media":"","overlay-type":"","overlay-color":"","overlay-opacity":"","overlay-gradient":""}},"ast-content-background-meta":{"desktop":{"background-color":"var(--ast-global-color-5)","background-image":"","background-repeat":"repeat","background-position":"center center","background-size":"auto","background-attachment":"scroll","background-type":"","background-media":"","overlay-type":"","overlay-color":"","overlay-opacity":"","overlay-gradient":""},"tablet":{"background-color":"var(--ast-global-color-5)","background-image":"","background-repeat":"repeat","background-position":"center center","background-size":"auto","background-attachment":"scroll","background-type":"","background-media":"","overlay-type":"","overlay-color":"","overlay-opacity":"","overlay-gradient":""},"mobile":{"background-color":"var(--ast-global-color-5)","background-image":"","background-repeat":"repeat","background-position":"center center","background-size":"auto","background-attachment":"scroll","background-type":"","background-media":"","overlay-type":"","overlay-color":"","overlay-opacity":"","overlay-gradient":""}},"footnotes":""},"categories":[1],"tags":[337,351,333,335,336,340,344,347,354,345,349,328,330,343],"class_list":["post-15473","post","type-post","status-publish","format-standard","has-post-thumbnail","hentry","category-uncategorized","tag-advanced-work-packaging","tag-awp","tag-control-accounts","tag-earned-value-management","tag-ekton-project-analytics","tag-engineering-management","tag-obs","tag-oil-and-gas-projects","tag-planning-packages","tag-project-controls-framework","tag-project-planning","tag-wbs","tag-work-breakdown-structure","tag-work-packages"],"yoast_head":"\nEkton Project Analytics<\/title>\n<meta name=\"description\" content=\"Learn how to build a deliverable-based WBS for Oil & Gas projects, avoid the #1 EVM mistake, and align scope, systems, and control accounts.\" \/>\n<meta name=\"robots\" content=\"index, follow, max-snippet:-1, max-image-preview:large, max-video-preview:-1\" \/>\n<link rel=\"canonical\" href=\"https:\/\/ekton.us\/zh\/wbs-control-accounts-and-cbs-erp-oil-gas-part-1-the-1-wbs-mistake-and-how-to-fix-it\/\" \/>\n<meta property=\"og:locale\" content=\"zh_CN\" \/>\n<meta property=\"og:type\" content=\"article\" \/>\n<meta property=\"og:title\" content=\"Ekton Project Analytics\" \/>\n<meta property=\"og:description\" content=\"Learn how to build a deliverable-based WBS for Oil & Gas projects, avoid the #1 EVM mistake, and align scope, systems, and control accounts.\" \/>\n<meta property=\"og:url\" content=\"https:\/\/ekton.us\/zh\/wbs-control-accounts-and-cbs-erp-oil-gas-part-1-the-1-wbs-mistake-and-how-to-fix-it\/\" \/>\n<meta property=\"og:site_name\" content=\"Ekton Project Analytics\" \/>\n<meta property=\"article:published_time\" content=\"2025-10-28T13:55:01+00:00\" \/>\n<meta property=\"article:modified_time\" content=\"2025-10-30T14:48:51+00:00\" \/>\n<meta property=\"og:image\" content=\"https:\/\/ekton.us\/wp-content\/uploads\/2025\/10\/WBS-Work-Breakdown-Structure-WBS-Oil-Gas-EVM-Earned-Value-Management-Control-Accounts-CBS1.jpg\" \/>\n\t<meta property=\"og:image:width\" content=\"1024\" \/>\n\t<meta property=\"og:image:height\" content=\"756\" \/>\n\t<meta property=\"og:image:type\" content=\"image\/jpeg\" \/>\n<meta name=\"author\" content=\"cassio antonio\" \/>\n<meta name=\"twitter:card\" content=\"summary_large_image\" \/>\n<meta name=\"twitter:label1\" content=\"\u4f5c\u8005\" \/>\n\t<meta name=\"twitter:data1\" content=\"cassio antonio\" \/>\n\t<meta name=\"twitter:label2\" content=\"\u9884\u8ba1\u9605\u8bfb\u65f6\u95f4\" \/>\n\t<meta name=\"twitter:data2\" content=\"5 \u5206\" \/>\n<script type=\"application\/ld+json\" class=\"yoast-schema-graph\">{\"@context\":\"https:\/\/schema.org\",\"@graph\":[{\"@type\":\"Article\",\"@id\":\"https:\/\/ekton.us\/wbs-control-accounts-and-cbs-erp-oil-gas-part-1-the-1-wbs-mistake-and-how-to-fix-it\/#article\",\"isPartOf\":{\"@id\":\"https:\/\/ekton.us\/wbs-control-accounts-and-cbs-erp-oil-gas-part-1-the-1-wbs-mistake-and-how-to-fix-it\/\"},\"author\":{\"name\":\"cassio antonio\",\"@id\":\"https:\/\/ekton.us\/en\/#\/schema\/person\/43ddff6915d4439064c684fc87fdc612\"},\"headline\":\"\u201cThe #1 WBS Mistake in Oil & Gas Projects \u2014 And How to Fix It with CBS, Control Accounts, and AWP\u201d\",\"datePublished\":\"2025-10-28T13:55:01+00:00\",\"dateModified\":\"2025-10-30T14:48:51+00:00\",\"mainEntityOfPage\":{\"@id\":\"https:\/\/ekton.us\/wbs-control-accounts-and-cbs-erp-oil-gas-part-1-the-1-wbs-mistake-and-how-to-fix-it\/\"},\"wordCount\":1006,\"commentCount\":0,\"publisher\":{\"@id\":\"https:\/\/ekton.us\/en\/#organization\"},\"image\":{\"@id\":\"https:\/\/ekton.us\/wbs-control-accounts-and-cbs-erp-oil-gas-part-1-the-1-wbs-mistake-and-how-to-fix-it\/#primaryimage\"},\"thumbnailUrl\":\"https:\/\/ekton.us\/wp-content\/uploads\/2025\/10\/WBS-Work-Breakdown-Structure-WBS-Oil-Gas-EVM-Earned-Value-Management-Control-Accounts-CBS1.jpg\",\"keywords\":[\"Advanced Work Packaging\",\"AWP\",\"Control Accounts\",\"Earned Value Management\",\"Ekton Project Analytics\",\"Engineering Management\",\"OBS\",\"Oil and Gas Projects\",\"Planning Packages\",\"Project Controls Framework\",\"Project Planning\",\"WBS\",\"Work Breakdown Structure\",\"Work Packages\"],\"articleSection\":[\"Uncategorized\"],\"inLanguage\":\"zh-Hans\",\"potentialAction\":[{\"@type\":\"CommentAction\",\"name\":\"Comment\",\"target\":[\"https:\/\/ekton.us\/wbs-control-accounts-and-cbs-erp-oil-gas-part-1-the-1-wbs-mistake-and-how-to-fix-it\/#respond\"]}]},{\"@type\":\"WebPage\",\"@id\":\"https:\/\/ekton.us\/wbs-control-accounts-and-cbs-erp-oil-gas-part-1-the-1-wbs-mistake-and-how-to-fix-it\/\",\"url\":\"https:\/\/ekton.us\/wbs-control-accounts-and-cbs-erp-oil-gas-part-1-the-1-wbs-mistake-and-how-to-fix-it\/\",\"name\":\"Ekton Project Analytics\",\"isPartOf\":{\"@id\":\"https:\/\/ekton.us\/en\/#website\"},\"primaryImageOfPage\":{\"@id\":\"https:\/\/ekton.us\/wbs-control-accounts-and-cbs-erp-oil-gas-part-1-the-1-wbs-mistake-and-how-to-fix-it\/#primaryimage\"},\"image\":{\"@id\":\"https:\/\/ekton.us\/wbs-control-accounts-and-cbs-erp-oil-gas-part-1-the-1-wbs-mistake-and-how-to-fix-it\/#primaryimage\"},\"thumbnailUrl\":\"https:\/\/ekton.us\/wp-content\/uploads\/2025\/10\/WBS-Work-Breakdown-Structure-WBS-Oil-Gas-EVM-Earned-Value-Management-Control-Accounts-CBS1.jpg\",\"datePublished\":\"2025-10-28T13:55:01+00:00\",\"dateModified\":\"2025-10-30T14:48:51+00:00\",\"description\":\"Learn how to build a deliverable-based WBS for Oil & Gas projects, avoid the #1 EVM mistake, and align scope, systems, and control accounts.\",\"breadcrumb\":{\"@id\":\"https:\/\/ekton.us\/wbs-control-accounts-and-cbs-erp-oil-gas-part-1-the-1-wbs-mistake-and-how-to-fix-it\/#breadcrumb\"},\"inLanguage\":\"zh-Hans\",\"potentialAction\":[{\"@type\":\"ReadAction\",\"target\":[\"https:\/\/ekton.us\/wbs-control-accounts-and-cbs-erp-oil-gas-part-1-the-1-wbs-mistake-and-how-to-fix-it\/\"]}]},{\"@type\":\"ImageObject\",\"inLanguage\":\"zh-Hans\",\"@id\":\"https:\/\/ekton.us\/wbs-control-accounts-and-cbs-erp-oil-gas-part-1-the-1-wbs-mistake-and-how-to-fix-it\/#primaryimage\",\"url\":\"https:\/\/ekton.us\/wp-content\/uploads\/2025\/10\/WBS-Work-Breakdown-Structure-WBS-Oil-Gas-EVM-Earned-Value-Management-Control-Accounts-CBS1.jpg\",\"contentUrl\":\"https:\/\/ekton.us\/wp-content\/uploads\/2025\/10\/WBS-Work-Breakdown-Structure-WBS-Oil-Gas-EVM-Earned-Value-Management-Control-Accounts-CBS1.jpg\",\"width\":1024,\"height\":756,\"caption\":\"WBS vs AWP Deliverable-oriented WBS EVM system setup Oil & Gas\"},{\"@type\":\"BreadcrumbList\",\"@id\":\"https:\/\/ekton.us\/wbs-control-accounts-and-cbs-erp-oil-gas-part-1-the-1-wbs-mistake-and-how-to-fix-it\/#breadcrumb\",\"itemListElement\":[{\"@type\":\"ListItem\",\"position\":1,\"name\":\"Home\",\"item\":\"https:\/\/ekton.us\/en\/\"},{\"@type\":\"ListItem\",\"position\":2,\"name\":\"\u201cThe #1 WBS Mistake in Oil & Gas Projects \u2014 And How to Fix It with CBS, Control Accounts, and AWP\u201d\"}]},{\"@type\":\"WebSite\",\"@id\":\"https:\/\/ekton.us\/en\/#website\",\"url\":\"https:\/\/ekton.us\/en\/\",\"name\":\"Ekton Project Analytics\",\"description\":\"Ekton Project Analytics: The data you need to make better decisions\",\"publisher\":{\"@id\":\"https:\/\/ekton.us\/en\/#organization\"},\"potentialAction\":[{\"@type\":\"SearchAction\",\"target\":{\"@type\":\"EntryPoint\",\"urlTemplate\":\"https:\/\/ekton.us\/en\/?s={search_term_string}\"},\"query-input\":{\"@type\":\"PropertyValueSpecification\",\"valueRequired\":true,\"valueName\":\"search_term_string\"}}],\"inLanguage\":\"zh-Hans\"},{\"@type\":\"Organization\",\"@id\":\"https:\/\/ekton.us\/en\/#organization\",\"name\":\"Ekton Project Analytics\",\"alternateName\":\"Ekton Project Analytics\",\"url\":\"https:\/\/ekton.us\/en\/\",\"logo\":{\"@type\":\"ImageObject\",\"inLanguage\":\"zh-Hans\",\"@id\":\"https:\/\/ekton.us\/en\/#\/schema\/logo\/image\/\",\"url\":\"https:\/\/www.ekton.us\/wp-content\/uploads\/2022\/12\/cropped-logo-ekton-1.png\",\"contentUrl\":\"https:\/\/www.ekton.us\/wp-content\/uploads\/2022\/12\/cropped-logo-ekton-1.png\",\"width\":512,\"height\":512,\"caption\":\"Ekton Project Analytics\"},\"image\":{\"@id\":\"https:\/\/ekton.us\/en\/#\/schema\/logo\/image\/\"},\"sameAs\":[\"https:\/\/www.linkedin.com\/company\/ekton-project-analytics\/mycompany\/?viewAsMember=true\",\"https:\/\/youtu.be\/EV9b-LZ-kT4\"]},{\"@type\":\"Person\",\"@id\":\"https:\/\/ekton.us\/en\/#\/schema\/person\/43ddff6915d4439064c684fc87fdc612\",\"name\":\"cassio antonio\",\"image\":{\"@type\":\"ImageObject\",\"inLanguage\":\"zh-Hans\",\"@id\":\"https:\/\/ekton.us\/en\/#\/schema\/person\/image\/\",\"url\":\"https:\/\/secure.gravatar.com\/avatar\/be40b80594dc19940fc1a2e03f7ba009353139437778e70be5906bb29e5fb795?s=96&d=mm&r=g\",\"contentUrl\":\"https:\/\/secure.gravatar.com\/avatar\/be40b80594dc19940fc1a2e03f7ba009353139437778e70be5906bb29e5fb795?s=96&d=mm&r=g\",\"caption\":\"cassio antonio\"},\"url\":\"https:\/\/ekton.us\/zh\/author\/acassio244\/\"}]}<\/script>\n","yoast_head_json":{"title":"Ekton Project Analytics","description":"Learn how to build a deliverable-based WBS for Oil & Gas projects, avoid the #1 EVM mistake, and align scope, systems, and control accounts.","robots":{"index":"index","follow":"follow","max-snippet":"max-snippet:-1","max-image-preview":"max-image-preview:large","max-video-preview":"max-video-preview:-1"},"canonical":"https:\/\/ekton.us\/zh\/wbs-control-accounts-and-cbs-erp-oil-gas-part-1-the-1-wbs-mistake-and-how-to-fix-it\/","og_locale":"zh_CN","og_type":"article","og_title":"Ekton Project Analytics","og_description":"Learn how to build a deliverable-based WBS for Oil & Gas projects, avoid the #1 EVM mistake, and align scope, systems, and control accounts.","og_url":"https:\/\/ekton.us\/zh\/wbs-control-accounts-and-cbs-erp-oil-gas-part-1-the-1-wbs-mistake-and-how-to-fix-it\/","og_site_name":"Ekton Project Analytics","article_published_time":"2025-10-28T13:55:01+00:00","article_modified_time":"2025-10-30T14:48:51+00:00","og_image":[{"width":1024,"height":756,"url":"https:\/\/ekton.us\/wp-content\/uploads\/2025\/10\/WBS-Work-Breakdown-Structure-WBS-Oil-Gas-EVM-Earned-Value-Management-Control-Accounts-CBS1.jpg","type":"image\/jpeg"}],"author":"cassio antonio","twitter_card":"summary_large_image","twitter_misc":{"\u4f5c\u8005":"cassio antonio","\u9884\u8ba1\u9605\u8bfb\u65f6\u95f4":"5 \u5206"},"schema":{"@context":"https:\/\/schema.org","@graph":[{"@type":"Article","@id":"https:\/\/ekton.us\/wbs-control-accounts-and-cbs-erp-oil-gas-part-1-the-1-wbs-mistake-and-how-to-fix-it\/#article","isPartOf":{"@id":"https:\/\/ekton.us\/wbs-control-accounts-and-cbs-erp-oil-gas-part-1-the-1-wbs-mistake-and-how-to-fix-it\/"},"author":{"name":"cassio antonio","@id":"https:\/\/ekton.us\/en\/#\/schema\/person\/43ddff6915d4439064c684fc87fdc612"},"headline":"\u201cThe #1 WBS Mistake in Oil & Gas Projects \u2014 And How to Fix It with CBS, Control Accounts, and AWP\u201d","datePublished":"2025-10-28T13:55:01+00:00","dateModified":"2025-10-30T14:48:51+00:00","mainEntityOfPage":{"@id":"https:\/\/ekton.us\/wbs-control-accounts-and-cbs-erp-oil-gas-part-1-the-1-wbs-mistake-and-how-to-fix-it\/"},"wordCount":1006,"commentCount":0,"publisher":{"@id":"https:\/\/ekton.us\/en\/#organization"},"image":{"@id":"https:\/\/ekton.us\/wbs-control-accounts-and-cbs-erp-oil-gas-part-1-the-1-wbs-mistake-and-how-to-fix-it\/#primaryimage"},"thumbnailUrl":"https:\/\/ekton.us\/wp-content\/uploads\/2025\/10\/WBS-Work-Breakdown-Structure-WBS-Oil-Gas-EVM-Earned-Value-Management-Control-Accounts-CBS1.jpg","keywords":["Advanced Work Packaging","AWP","Control Accounts","Earned Value Management","Ekton Project Analytics","Engineering Management","OBS","Oil and Gas Projects","Planning Packages","Project Controls Framework","Project Planning","WBS","Work Breakdown Structure","Work Packages"],"articleSection":["Uncategorized"],"inLanguage":"zh-Hans","potentialAction":[{"@type":"CommentAction","name":"Comment","target":["https:\/\/ekton.us\/wbs-control-accounts-and-cbs-erp-oil-gas-part-1-the-1-wbs-mistake-and-how-to-fix-it\/#respond"]}]},{"@type":"WebPage","@id":"https:\/\/ekton.us\/wbs-control-accounts-and-cbs-erp-oil-gas-part-1-the-1-wbs-mistake-and-how-to-fix-it\/","url":"https:\/\/ekton.us\/wbs-control-accounts-and-cbs-erp-oil-gas-part-1-the-1-wbs-mistake-and-how-to-fix-it\/","name":"Ekton Project Analytics","isPartOf":{"@id":"https:\/\/ekton.us\/en\/#website"},"primaryImageOfPage":{"@id":"https:\/\/ekton.us\/wbs-control-accounts-and-cbs-erp-oil-gas-part-1-the-1-wbs-mistake-and-how-to-fix-it\/#primaryimage"},"image":{"@id":"https:\/\/ekton.us\/wbs-control-accounts-and-cbs-erp-oil-gas-part-1-the-1-wbs-mistake-and-how-to-fix-it\/#primaryimage"},"thumbnailUrl":"https:\/\/ekton.us\/wp-content\/uploads\/2025\/10\/WBS-Work-Breakdown-Structure-WBS-Oil-Gas-EVM-Earned-Value-Management-Control-Accounts-CBS1.jpg","datePublished":"2025-10-28T13:55:01+00:00","dateModified":"2025-10-30T14:48:51+00:00","description":"Learn how to build a deliverable-based WBS for Oil & Gas projects, avoid the #1 EVM mistake, and align scope, systems, and control accounts.","breadcrumb":{"@id":"https:\/\/ekton.us\/wbs-control-accounts-and-cbs-erp-oil-gas-part-1-the-1-wbs-mistake-and-how-to-fix-it\/#breadcrumb"},"inLanguage":"zh-Hans","potentialAction":[{"@type":"ReadAction","target":["https:\/\/ekton.us\/wbs-control-accounts-and-cbs-erp-oil-gas-part-1-the-1-wbs-mistake-and-how-to-fix-it\/"]}]},{"@type":"ImageObject","inLanguage":"zh-Hans","@id":"https:\/\/ekton.us\/wbs-control-accounts-and-cbs-erp-oil-gas-part-1-the-1-wbs-mistake-and-how-to-fix-it\/#primaryimage","url":"https:\/\/ekton.us\/wp-content\/uploads\/2025\/10\/WBS-Work-Breakdown-Structure-WBS-Oil-Gas-EVM-Earned-Value-Management-Control-Accounts-CBS1.jpg","contentUrl":"https:\/\/ekton.us\/wp-content\/uploads\/2025\/10\/WBS-Work-Breakdown-Structure-WBS-Oil-Gas-EVM-Earned-Value-Management-Control-Accounts-CBS1.jpg","width":1024,"height":756,"caption":"WBS vs AWP Deliverable-oriented WBS EVM system setup Oil & Gas"},{"@type":"BreadcrumbList","@id":"https:\/\/ekton.us\/wbs-control-accounts-and-cbs-erp-oil-gas-part-1-the-1-wbs-mistake-and-how-to-fix-it\/#breadcrumb","itemListElement":[{"@type":"ListItem","position":1,"name":"Home","item":"https:\/\/ekton.us\/en\/"},{"@type":"ListItem","position":2,"name":"\u201cThe #1 WBS Mistake in Oil & Gas Projects \u2014 And How to Fix It with CBS, Control Accounts, and AWP\u201d"}]},{"@type":"WebSite","@id":"https:\/\/ekton.us\/en\/#website","url":"https:\/\/ekton.us\/en\/","name":"Ekton Project Analytics","description":"Ekton Project Analytics: The data you need to make better decisions","publisher":{"@id":"https:\/\/ekton.us\/en\/#organization"},"potentialAction":[{"@type":"SearchAction","target":{"@type":"EntryPoint","urlTemplate":"https:\/\/ekton.us\/en\/?s={search_term_string}"},"query-input":{"@type":"PropertyValueSpecification","valueRequired":true,"valueName":"search_term_string"}}],"inLanguage":"zh-Hans"},{"@type":"Organization","@id":"https:\/\/ekton.us\/en\/#organization","name":"Ekton Project Analytics","alternateName":"Ekton Project Analytics","url":"https:\/\/ekton.us\/en\/","logo":{"@type":"ImageObject","inLanguage":"zh-Hans","@id":"https:\/\/ekton.us\/en\/#\/schema\/logo\/image\/","url":"https:\/\/www.ekton.us\/wp-content\/uploads\/2022\/12\/cropped-logo-ekton-1.png","contentUrl":"https:\/\/www.ekton.us\/wp-content\/uploads\/2022\/12\/cropped-logo-ekton-1.png","width":512,"height":512,"caption":"Ekton Project Analytics"},"image":{"@id":"https:\/\/ekton.us\/en\/#\/schema\/logo\/image\/"},"sameAs":["https:\/\/www.linkedin.com\/company\/ekton-project-analytics\/mycompany\/?viewAsMember=true","https:\/\/youtu.be\/EV9b-LZ-kT4"]},{"@type":"Person","@id":"https:\/\/ekton.us\/en\/#\/schema\/person\/43ddff6915d4439064c684fc87fdc612","name":"cassio antonio","image":{"@type":"ImageObject","inLanguage":"zh-Hans","@id":"https:\/\/ekton.us\/en\/#\/schema\/person\/image\/","url":"https:\/\/secure.gravatar.com\/avatar\/be40b80594dc19940fc1a2e03f7ba009353139437778e70be5906bb29e5fb795?s=96&d=mm&r=g","contentUrl":"https:\/\/secure.gravatar.com\/avatar\/be40b80594dc19940fc1a2e03f7ba009353139437778e70be5906bb29e5fb795?s=96&d=mm&r=g","caption":"cassio antonio"},"url":"https:\/\/ekton.us\/zh\/author\/acassio244\/"}]}},"_links":{"self":[{"href":"https:\/\/ekton.us\/zh\/wp-json\/wp\/v2\/posts\/15473","targetHints":{"allow":["GET"]}}],"collection":[{"href":"https:\/\/ekton.us\/zh\/wp-json\/wp\/v2\/posts"}],"about":[{"href":"https:\/\/ekton.us\/zh\/wp-json\/wp\/v2\/types\/post"}],"author":[{"embeddable":true,"href":"https:\/\/ekton.us\/zh\/wp-json\/wp\/v2\/users\/11"}],"replies":[{"embeddable":true,"href":"https:\/\/ekton.us\/zh\/wp-json\/wp\/v2\/comments?post=15473"}],"version-history":[{"count":17,"href":"https:\/\/ekton.us\/zh\/wp-json\/wp\/v2\/posts\/15473\/revisions"}],"predecessor-version":[{"id":15533,"href":"https:\/\/ekton.us\/zh\/wp-json\/wp\/v2\/posts\/15473\/revisions\/15533"}],"wp:featuredmedia":[{"embeddable":true,"href":"https:\/\/ekton.us\/zh\/wp-json\/wp\/v2\/media\/15478"}],"wp:attachment":[{"href":"https:\/\/ekton.us\/zh\/wp-json\/wp\/v2\/media?parent=15473"}],"wp:term":[{"taxonomy":"category","embeddable":true,"href":"https:\/\/ekton.us\/zh\/wp-json\/wp\/v2\/categories?post=15473"},{"taxonomy":"post_tag","embeddable":true,"href":"https:\/\/ekton.us\/zh\/wp-json\/wp\/v2\/tags?post=15473"}],"curies":[{"name":"wp","href":"https:\/\/api.w.org\/{rel}","templated":true}]}}<!-- This website is optimized by Airlift. Learn more: https://airlift.net. Template:. Learn more: https://airlift.net. Template: 69c48321db888a24c8df39fc. Config Timestamp: 2026-03-26 00:51:44 UTC, Cached Timestamp: 2026-04-15 22:36:41 UTC -->